Touchstone Exploration first gas from the Cascadura facility date given

Touchstone Exploration

Touchstone Exploration Inc. (TSX, LON:TXP) has reported that on February 24, 2023, the Company was notified by The National Gas Company of Trinidad and Tobago Limited that they expect to be ready to receive first gas from the Cascadura natural gas and associated liquids facility on or about June 30, 2023.

Touchstone remains on track to complete the Cascadura facility prior to this date to ensure production can commence as soon as NGC is in a position to receive first gas. The approximate construction status of the Cascadura facility is as follows:

•the civil and concrete foundation work for the main process facility equipment is complete;
•the flare stack is procured, with the associated foundation work commencing imminently;
•the communication tower is approximately 80 percent complete;
•the pipe racks are approximately 90 percent assembled with hydrotesting initiated, and the units are expected to arrive at the facility within the next three weeks;
•on-site condensate tanks are approximately 65 percent complete;
•the compressors, separators, and vapour recovery units have been safely transported to the facility; and
•all process equipment for the facility has been acquired.

Paul Baay, Touchstone Exploration President and Chief Executive Officer, commented:

“We are encouraged to have received an expected first gas date from NGC. Although this is later than we were anticipating, we can now plan the final phase of our various work streams to minimize costs and optimize services.

First gas from Cascadura will be a transformative achievement for Touchstone, and we thank shareholders for their continued support and patience as we work towards this significant milestone.  

We expect that the funds raised late last year and our current base production will allow us to complete drilling the Royston-1X well and prepare our next development locations at Cascadura while we finalize construction of the Cascadura facility.“

Share on:
Find more news, interviews, share price & company profile here for:

Latest Company News

Touchstone Exploration Sees Pricing Upside and Operational Catalysts in Latest Research Note from Cavendish

Touchstone Exploration’s latest Cavendish note highlights stronger pricing, operational catalysts and potential gas contract upside across its Trinidad asset base.

Touchstone seeks longer runway for Ortoire exploration in Trinidad

Touchstone Exploration is seeking a new exploration term for Trinidad’s Ortoire block, keeping investor attention on licence timing, commitments and future drilling optionality.

Touchstone Exploration posts higher Q1 revenue on improved commodity pricing

Touchstone Exploration recorded first quarter 2026 revenue of $12.5 million, supported by stronger realized oil and gas prices, while continuing recapitalization efforts and progressing key development projects in Trinidad.

Touchstone positions Central Block for expanded Trinidad gas development

Touchstone Exploration showcased its Central Block gas infrastructure and Carapal Ridge development plans as the company works to expand Trinidad gas production following operatorship of the assets.

Touchstone moves Cascadura gas expansion closer to delivery

Touchstone moves Cascadura closer to higher gas output with major compressor equipment now delivered to site.

Touchstone pushes for scale in Trinidad’s onshore market

Touchstone is trying to turn a larger onshore footprint in Trinidad into a step-change in production, with execution now the main issue for investors to watch.

Search